Fisher Associates provided specialized construction engineering services for the Phase 2 bridge installations along Route 15 in Lindley, NY. Supporting the steel erection subcontractor, the team developed detailed erection plans for three large steel girder bridges, including both single- and multi-span structures. Using 150- and 275-ton cranes, Fisher evaluated crane placement, lift capacities, and erection sequencing to ensure safe and efficient operations. The work also included verifying girder weights, designing temporary shoring towers, and analyzing the impact of crane loads on bridge substructures. Through careful coordination and structural analysis, Fisher helped streamline complex erection activities while maintaining safety and construction efficiency.